Posted on: September 1, 2023

Sewage main in west Fillmore Update

Sewer Repair Trench Shoring (jpg)

FOR IMMEDIATE RELEASE:

City of Fillmore 

 

Sewage main in west Fillmore - Update

FILLMORE, CALIFORNIA – September 13, 2023 –   Sewer Repair Project Update 

GOOD NEWS:  We are nearing completion! On Saturday, September 7, 2023, Toro completed concrete work and grinding of C Street pavement.  On September 12, 2023, the patches and trenches were base paved and all of the paving in Caltrans right of way was completed. Today, they are scheduled to pave the final lift on C Street.  On September 17th the team is scheduled to remove the closures from SR126 and C Street and place the traffic signal to normal operation with ALL LANES OPEN.  In the coming two weeks they will finalize the striping and punch list items so we can close this project out!


For questions and further information regarding this incident, please contact Troy Spayd, Municipal Services Director/ Utilities Engineer at 805-524-3701 ext. 232 or via email at tspayd@fillmoreca.gov

 

Please visit www.fillmoreca.com  and follow us on Facebook, Instagram, Twitter, and LinkedIn. 

 

Community Contact:

Name: Erika Herrera-Terriquez

Title: Assistant City Manager

Phone: 805-946-1712

Email: eherrera@fillmoreca.gov

 


FOR IMMEDIATE RELEASE:

City of Fillmore 

 

Sewage main in west Fillmore - Update

FILLMORE, CALIFORNIA – July 27, 2023 –   Sewer Repair Project Update 

The new traffic control in SR126 continues to operate  and work has been moving along very well. All businesses adjacent to the work area are open and accessible. Both of the church driveways and the Grocery Outlet driveway at The STOP on C Street are open with access only from River Street.

 

The new 24” PVC line is installed up to just south of the jack and bore pit just south of SR 126, ready for connection once the encased line is completed under the highway.   The Jack and Bore pit and receiving pit have been excavated and the encasement has been put on hold pending re-design to accommodate elevations in the field not matching the design. This will potentially delay the completion of the repair project by a week to ten days, but the goal is still to complete the repairs before the end of August.

 

We are processing change order to replace the collapsed manhole plus reconditioning the next manhole west in 12” PVC in SR126, as it is corroded and in need of replastering over the brick.   This will eliminate the need to continue bypassing the D Street sewer while we complete the study/design/construction docs for Phase 2 project and save that cost as well.

 

City staff and contractors are working hard to finish this project and let the residents of Fillmore get back to life without the bypass pumps disrupting traffic flow and residential neighborhoods. 


For questions and further information regarding this incident, please contact Troy Spayd, Municipal Services Director/ Utilities Engineer at 805-524-3701 ext. 232 or via email at tspayd@fillmoreca.gov

 

Please visit www.fillmoreca.com  and follow us on Facebook, Instagram, Twitter, and LinkedIn. 

 

Community Contact:

Name: Erika Herrera-Terriquez

Title: Assistant City Manager

Phone: 805-946-1712

Email: eherrera@fillmoreca.gov

 

 

###



FILLMORE, CALIFORNIA – July 10, 2023 – On March 15, 2023, a sewer main in west Fillmore suffered collapse on the intersection of C Street and Ventura Street (SR 126). The City contracted Ferreira Construction to assist with rerouting the flow of wastewater through other sewer mains. Since then, after bidding out the project for “C’ Street Emergency Sewer Repair Project, Spec. No.23-01E on May 9, 2023, the City awarded the contract to Toro Enterprises in the amount of $3,575,033.55. 

 

Since the award of the contract, the following work/updates have taken place:

  1. On June 14, 2023, Caltrans issued the Encroachment Permit for work in State Right to the City of Fillmore. 
  2. Dewatering in C Street began on Friday, June 16, 2023.
  3. Work on Phase 1A commenced on Monday, June 19, 2023.  Phase 1A entails the tie in of a new sewer manhole in the center of River and C Street and installation of new sewer in the southern portion of C Street, north of River Street.
  4. Toro has completed all the work that they can in the existing traffic control set up in the State Right of Way, including some of the dewatering drilling.  
  5. Toro will continue to work on completing the project. 

For questions and further information regarding this incident, please contact Troy Spayd, Municipal Services Director/ Utilities Engineer at 805-524-3701 ext. 232 or via email at tspayd@fillmoreca.gov

 

Please visit www.fillmoreca.com  and follow us on Facebook, Instagram, Twitter, and LinkedIn. 

 

Community Contact:

Name: Erika Herrera-Terriquez

Title: Assistant City Manager

Phone: 805-946-1712

Email: eherrera@fillmoreca.gov

 

 

###

 